Fibre Deployment Update Jan. 2017

Post date: 29-Jan-2017 00:41:39

Due to the processes and issues of obtaining multiple wayleaves on the route to Sigingstone, that has taken a significant amount of time to resolve with the multiple landowners, this has resulted in additional delays until the FTTP service will be ready for service and order.

Openreach's current plans are estimating a completion date of March 2017 for the infrastructure. This will be followed by the commissioning process which can take 6-8 weeks.

Taking this into account then you can be looking a the FTTP service within Sigingstone to be ready for service sometime in May 2017 however this date will move later into 2017 if there are further delays.