Fibre Deployment Update Nov. 2016

posted 20 Nov 2016, 14:08 by Sigingstone Webmaster   [ updated 28 Jan 2017, 16:44 ]
This information has been superseded and is no longer valid. Please check the most recent updates.

The deployment works have slipped by approximately 3 weeks due to a delay in receiving approvals from the VoG Council and highways for some ground works required within the village.

The current timeline is:
  • All the deployment ground works to be finished before the Christmas period, this will then be followed by the commissioning process (testing, updating systems and altering Communication Providers).
  • FTTP infrastructure Ready for Service around Mid-Late January 2017