Fibre Deployment Update Nov. 2016

Post date: 20-Nov-2016 22:08:13

This information has been superseded and is no longer valid. Please check the most recent updates.

The deployment works have slipped by approximately 3 weeks due to a delay in receiving approvals from the VoG Council and highways for some ground works required within the village.

The current timeline is:

    • All the deployment ground works to be finished before the Christmas period, this will then be followed by the commissioning process (testing, updating systems and altering Communication Providers).

    • FTTP infrastructure Ready for Service around Mid-Late January 2017